System Verification Units

Подпись: 13In addition to the DOE-NASA units, NASA Lewis participated with the Bureau of Reclamation in the experimentation with two other tur­bines near Medicine Bow, WY. Both of these machines were designated as system verification units (SVU) because of their purpose of veri­fying the concept of integrating wind turbine generators with hydro­electric power networks. This was viewed as an important step in the Bureau of Reclamation’s long-range program of supplementing hydro­electric power generation with wind turbine power generation. One of the two turbines was a new design developed by the Hamilton Standard Division of United Technologies Corp., a 4-megawatt WTS-4 system, in the Medicine Bow area. A Swedish company, Karlskronavarvet (KKRV), was selected as a major subcontractor responsible for the design and fabrication of the nacelle hardware. The WTS-4 had a two-blade fiber­glass downwind rotor that was 256.4 feet in diameter. For over 20 years, this 4-megawatt machine remained the largest power rated wind turbine generator ever built. In a reverse role, an additional 3-megawatt version of the same machine was built for the Swedish government, with KKRV as the prime contractor and Hamilton Standard as the subcontractor.[1507]

The other SVU turbine was a Mod-2 design. While NASA engineers determined that the initial Mod-2 wind turbine generator performance was acceptable, they noted areas where improvement was needed. The problems encountered were primarily hardware-oriented and were attributed to fabrication or design deficiencies. Identification of these problems led to a number of modifications, including changes in the hydraulic, electric, and control systems; rework of the rotor hub flange; addition of a forced-lubrication system; and design of a new low-speed shaft.

Подпись: 13 System Verification Units

Third-Generation Advanced Multimegawatt Wind Turbines—The Mod-5 Program (1980-1988)

The third-generation (Mod-5) program, which started in 1980, was intended to incorporate the experiences from the earlier DOE-NASA wind turbines, especially the Mod-2 experiences, into a final proof-of – concept system for commercial use by an electric utility company. Two construction contracts were awarded to build the Mod-5 turbines—one unit to General Electric, which was designated the Mod-5A, and one unit to Boeing, which was designated the Mod-5B. As intermediate steps between the Mod-2 and Mod-5, two conceptual studies were undertaken for fabrication of both an advanced large wind turbine designated the Mod-3 and a medium turbine designated the Mod-4. Likewise, both a large-scale Mod-5 and medium-scale Mod-6 were planned as the final Wind Energy Program turbines. The Mod-3 and Mod-4 studies, however, were not carried through to construction of the turbines, and the Mod-6 program was canceled because of budget constraints and changing pri­orities resulting from a decline in oil prices following the end of the oil
crisis of the 1970s. Also, General Electric chose not to proceed beyond the design phase with its Mod-5A. As a result, only the Boeing Mod-5B was constructed and placed into power utility service.[1508]

Подпись: 13Although its design was never built, General Electric did complete the detailed design work and all of the significant development tests and documented the entire Mod-5A program. The planned Mod-5A system contained many interesting features that NASA Lewis chose to preserve for future reference. The Mod-5A wind turbine was expected to generate electricity at a cost competitive with conventional forms of power gen­eration once the turbines were in volume production. The program was divided into three phases: conceptual design, which was completed in March 1981; preliminary design, which was completed in May 1982; and final design, which was started in June 1982. The Mod-5A was planned to have a 7.3-megawatt generator, a 400-foot-diameter two-bladed tee­tered rotor, and hydraulically actuated ailerons over the outboard 40 percent of the blade span to regulate the power and control shutdown. The blades were to be made of epoxy-bonded wood laminates. The yaw drive was to include a hydraulically actuated disk brake system, and the tower was to be a soft-designed welded steel plate cylindrical shell with a conical base. The Mod-5A was designed to operate in wind speeds of between 12 and 60 mph at hub height. The system was designed for auto­matic unattended operation and for a design life of 30 years.[1509]

The Mod-5B, which was the only Mod-5 unit built, was physically the world’s largest wind turbine generator. The Mod-5B represented very advanced technology, including an upwind teetered rotor, compact plan­etary gearbox, pitchable tip blade control, soft-shell-type tower, and a variable-speed electrical induction generator/control system. Variable speed control enabled the turbine speed to vary with the wind speed, resulting in an increase energy capture and a decrease in fatigue loads on the drive train. The system underwent a number of design changes before the final fabricated version was built. For example, the turbine originally was planned to have a blade swept diameter of 304 feet. This was increased to 420 feet and finally reduced to 320 feet because of the use of blade steel tips and control improvements. Also, the tur­bine generator was planned initially to be rated at 4.4 megawatts. This
was increased to 7.2 megawatts and then decreased to the final version 3.2 megawatts because of development of better tip control and load management. The rotor weighed 319,000 pounds and was mounted on a 200-foot tower. Extensive testing of the Mod-5B system was con­ducted, including 580 hours of operational testing and 660 hours of per­formance and structural testing. Performance testing alone generated over 72 reports reviewing test results and problems resolved.[1510]

Подпись: 13The Mod-5B was the first large-scale wind turbine to operate suc­cessfully at variable rotational speeds, which varied from 13 to 17.3 revolutions per minute depending on the wind speed. In addition, the Mod-5B was the first large wind turbine with an apparent possibil­ity of lasting 30 years. The turbine, with a total system weight of 1.3 million pounds, was installed at Kahuku on the north shore of Oahu, HI, in 1987 and was operated first by Hawaiian Electric Incorporated and later by the Makani Uwila Power Corporation. The turbine started rated power rotation July 1, 1987. In January 1988, the Mod-5B was sold to the power utility, which continued to operate the unit as part of its power generation network until the small power utility ceased operations in 1996. In 1991, the Mod-5B produced a single wind tur­bine record of 1,256 megawatthours of electricity. The Mod-5B was oper­ated in conjunction with 15 Westinghouse 600-kilowatt wind turbines. While the Westinghouse turbines were not part of the NASA program, the design of the turbines combined successful technology from NASA’s Mod-0A and Mod-2 programs.[1511]

The Mod-5B, which represented a significant decrease over the Mod-2 turbines in the cost of production of electricity, was designed for the sole purpose of providing electrical power for a major utility network. To achieve this goal, a number of changes were made over the Mod-2 systems, including changes in concepts, size, and design refinements. These changes were reflected in more than 20 engineering studies, which addressed issues such as variable pitch versus fixed pitch, optimum machine size, steel shell versus truss tower, blade aerodynamics, mate­rial selection, rotor control, tower height, cluster optimization, and
gearbox configuration. For example, the studies indicated that loads problem was the decisive factor with regard to the use of a partial span variable pitch system rather than a fixed pitch rotor system, dynamic simulation led to selection of the variable speed generator, analysis of operational data enabled a significant reduction in the weight and size of the gearbox, and the development of weight and cost trend data for use in size optimization studies resulted in the formulation of machine sizing programs.[1512]

Подпись: 13A number of design elements resulted in significant contributions to the success of the Mod-5B wind turbine. Aerodynamic improvement over the Mod-2, including improvements in vortex generators, trailing edge tabs, and better shape control, resulted in an 18-percent energy capture increase. Improved variable speed design resulted in an increase of greater than 7 percent (up to as high as 11 percent) over an equiva­lent synchronous generator system. Both cycloconverter efficiency and control optimization of rotor speed versus wind speed proved to be bet­ter than anticipated. Use of the variable speed generator system to con­trol power output directly, as opposed to the pitch power control on the Mod-2, substantially reduced blade activity, especially at below rated power levels. The variable speed design also resulted in a substantial reduction in structural loads. Adequate structural integrity was dem­onstrated for all stress measurement locations. Lessons learned during the earlier operation of the Mod-2 systems resulted in improved yaw and pitch systems. Extensive laboratory simulation of control hardware and software likewise reduced control problems compared with Mod-2 systems.[1513] In summary, the Mod-5B machine represented a reliable proof-of-concept large horizontal-axis wind turbine conversion system capable of long-life production of electricity into a power grid system, thus fulfilling the DOE-NASA program objectives.

The Mod-5B was the last DOE-NASA wind turbine generator built under the Federal Wind Energy Program. In his paper on the Mod-5B wind turbine system, Boeing engineer R. R. Douglass noted the follow­ing size versus cost problem relating to the purchase of large wind tur­bines faced by power utility companies:

. . . large scale commercialization of large wind turbines suf­fers from the chicken and egg syndrome. That is, costs of units are so high when produced one or two at a time on prototype tooling that the utilities can scarcely afford to buy them. On the other hand, industry cannot possibly afford to invest the huge capital required for an automated high rate production capability without an established order base. To break this log jam will require a great deal of cooperation between govern­ment, industry, and the utilities.[1514]

Подпись: 13Boeing noted, however, in its final Mod-5B report that: "In summary the Mod-5B demonstrated the potential to generate at least 11 percent more revenue at a given site than the original design goal. It also dem­onstrated that multi-megawatt class wind turbines can be developed with high dependability which ultimately should show up in reduced operation and maintenance costs.”[1515]